Conger simultaneously completed both the West and East school projects. We added a new auxiliary gym on the front of the building for practices and new administrative offices.  These were active campuses with 2000-3000 students using the facilities while under construction.  Multi-story classroom additions were added to the back of cafeteria, directly adjacent to existing classrooms.  Our self-perform capabilities allowed us to be flexible with our construction schedule so that we created as little distraction as possible during classes and exams.  Conger created new corridor across main street, took off the roof exposing the band room & instruments.  This required creative ways to protect these things while we were able to get the structure up, concrete poured and roof on in a 3 week time frame